New Church Project - Time line

  • Jan 2010 – Project Kick-Off
  • Jan-Dec 2010 – Concept Development
  • Dec 2010 – Site Plan submitted to Township
  • Mar 2011 – Site Plan Approved
  • Jul 2011 – Land purchase completed after due diligence
  • Mar 2011-Feb 2012 – Design/Development, Site Plan review compliance
  • Feb 2012 – Site Plan first resubmission for compliance
  • August 2012 – Construction Loan LOI received
  • Oct 2012 – Site Plan second resubmission for compliance
  • Oct 2012 – Construction Drawing complete 95%
  • Nov 2013 – Construction Started